Review Agenda Item
Meeting Date: 10/16/2024 - 7:00 PM
Category: Property & Supply - Transportation
Type: Action
Subject: 13.6 Change Order HC-008
:
Enclosure
File Attachment:
Summary:
Funding:
Recommendation: Approving Change Order HC-008 with Lugaila Mechanical Inc., for cost associated with revisions to existing ductwork at the undersized supply trunk line to RTU-11, reconfiguration of existing ductwork in classroom C206, B201, B213 to accommodate skylight locations and rework of the boiler room exhaust ductwork to accommodate the new exhaust fan and motorized louver. Total Cost of $6,325.84.
Approvals:
Recommended By:
Signed By:
Lisa Wilson - Secretary - Superintendent
Signed By:
Jerri Lynn Lippert - Superintendent