Meeting Date:
|
8/21/2024 - 7:00 PM
|
Category:
|
Property & Supply - Transportation
|
Type:
|
Action
|
Subject:
|
13.7 Change Order GC-041
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
|
Funding:
|
|
Recommendation:
|
Authorizing change order GC-041 with Hudson Group to furnish and install install dowels and epoxy grout into the existing grade beam along column line 57.1 for the new LGI room foundation in the total amount of $ 5,045.67.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Lisa Wilson - Secretary - Superintendent
|
|
Signed By:
|
|
Jerri Lynn Lippert - Superintendent
|
|
|
|
|
|
|
|