13.5 Change Order GC-016
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
|
Funding:
|
|
Recommendation:
|
Approving change order GC-016 with the Hudson Group to remove the remaining block wall found within and below the existing concrete floor slab at storage room A222. Contractor to demolish block and patch concrete slab for a smooth and level floor area. Total cost of $1,612.00.
|