Meeting Date:
|
3/20/2024 - 7:00 PM
|
Category:
|
Property & Supply - Transportation
|
Type:
|
Action
|
Subject:
|
13.7 Change Order EC-010
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
|
Funding:
|
|
Recommendation:
|
Approving Change Order EC-010 with Allegheny City Electric to remove and relocate electrical conduit that was inline with the rework of mechanical duct for the girls gang restroom (RB-12). Work was completed on a time and material basis for a total cost of $1,158.11.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Lisa Wilson - Secretary - Superintendent
|
|
Signed By:
|
|
Jerri Lynn Lippert - Superintendent
|
|
|
|
|
|
|
|