Subject:
|
13.9 Change Order EC-009
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
|
Funding:
|
|
Recommendation:
|
Approving change order EC-009 with Allegheny City Electric to replace the existing site lighting circuit that was damaged during Phase 2 demolition. New circuiting was run through the building addition to re-energize the existing site lighting until the new site lighting is completed summer of 2024. Total cost of $8,241.81.
|