Review Agenda Item
Meeting Date: 6/19/2024 - 7:00 PM
Category: Property & Supply - Transportation
Type: Action
Subject: 13.4 Change Order GC-034
:
Enclosure
File Attachment:
Summary:
Funding:
Recommendation: Approving Change Order GC-034 with the Hudson Group to modify the new underground storm system between CB-1.1 and the new pond, increase underground piping to 18” to accommodate an additional 8” line connection to the storm system. Total cost of $5,234.00.
Approvals:
Recommended By:
Signed By:
Lisa Wilson - Secretary - Superintendent
Signed By:
Jerri Lynn Lippert - Superintendent