13.9 Change Order EC-018
|
:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
|
Funding:
|
|
Recommendation:
|
Approving Change Order EC-018 with Allegheny City Electric to remove an existing electrical panel during Phase 5 of the project that was not identified on the previous renovation documents from June 2000. A temporary panel was required to be installed to provide power to existing circuits feeding AHU-2 and phase 7 classrooms. Total Cost of $9,923.11.
|